Junior High Construction Update 10/24/18

At Thomas Ewing, the roofing is complete on the two story classroom section of the building while exterior brick installation continues.  Hydronic pipes are being installed on the first floor while metal drywall studs and ventilation duct work installation continues on the second floor.  In the main entrance section, roofing and electrical conduit are being installed.  Exterior brick is also being installed in the single story classroom section along with electrical conduit installation.  Concrete masonry block continues to be erected in the gymnasium and cafeteria sections while roof drains, concrete block insulation, and soffits are being installed throughout the building. 
 
At General Sherman, the building pad has been stoned and the footers are now being poured.  Concrete masonry block installation will follow.  Earthwork continues in the parking areas to prepare the base for both parking areas.
Steve Wigton
Superintendent




Back to School News      Print News Article
Contact Us
Lancaster City School District345 East Mulberry Street
Lancaster, OH 43130
View Map & Directions
Phone: 740.687.7300
Fax: 740.687.7303