Junior High Construction Update 12/19/19

At Thomas Ewing, work has begun to construct the entryway to the building and the gas line for the building has been installed.  On the building exterior, brick and roofing are being installed on the gymnasium section of the building and concrete block installation and roofing are being sprayed on the outside of the cafeteria section.  On the inside of the building, HVAC ductwork is being installed in the two story classroom section while the sprinkler system, HVAC water pipes, and electric rough ins are being installed in the single story classroom section.  Storm pipes, HVAC ductwork and HVAC water pipes are being installed in the gymnasium section and internal concrete masonry block and electrical rough ins are being installed in the cafeteria section.  

At General Sherman, the concrete foundations for the building sections are complete.  RVM Construction has completed construction of the exterior concrete masonry block walls for the first floor of the two story classroom section of the building and are constructing exterior concrete masonry block walls for the main entrance section.  Claypool Electric is roughing in conduit and boxes in coordination with the masons.  Underground sanitary, storm and acid waste lines are being installed in the two story classroom section.  The base for the parking lots and driveway entrance is complete and gravel is being added to these areas.

Steve Wigton
Superintendent





Back to School News      Print News Article
Contact Us
Lancaster City School District345 East Mulberry Street
Lancaster, OH 43130