JH Construction Update 2/6/19

At Thomas Ewing, front entrance brick continues to be installed as weather permits.  Drywall continues to be installed in the two story classroom section of the building along with plumbing, HVAC and electrical items.  In the single story classroom section, drywall and water line installation continues.  HVAC, sprinkler system, window and exterior brick installation are in progress in the gymnasium section.  In the cafeteria section, sprinkler system, windows, and metal roofing are being installed.

At General Sherman, structural steel columns and beams are being set in the two story classroom section of the building and interior concrete masonry bearing walls, along with electrical and plumbing rough ins, are complete.  In the single story classroom section, digging for the underground electric lines is complete and underground water lines are being installed.

Steve Wigton
Superintendent

 

Thomas Ewing - store front windows installed 2019

 

General Sherman - walls being erected - Feb. 2019





Back to School News      Print News Article
Contact Us
Lancaster City School District345 East Mulberry Street
Lancaster, OH 43130