Junior High Construction Update 4/24/2019

At Thomas Ewing, earthwork is underway on the turn lane, sidewalks and curbs.  Throughout the building, operable windows and HVAC control wiring are being installed as well as exterior brick cleaning.  Drywall, chilled beam units, and ceiling grids are being installed in the two story classroom section of the building.  In the main entrance section, block fill, first coat of paint, and domestic water line installation are in progress.  Drywall installation continues in the gymnasium section while technology and electric lines are being pulled.  In the cafeteria section, sprinkler branch lines, technology wires, and electrical rough ins are being installed.

At General Sherman, the gymnasium and stage areas are being prepared for the concrete floor to be poured.  In the main section of the building, internal concrete block walls, in-wall plumbing lines, overhead conduit and external concrete block insulation are being installed.   Internal concrete block walls, in-wall plumbing lines, and overhead conduit are also being installed in the single story classroom section.  In the two story classroom section, overhead HVAC water pipes and air ducts are being installed on the first floor while roof bar joists have been installed on the second floor.

Steve Wigton
Superintendent

 

GS Construction Site April 2019

GS Construction site April 2019

TE Construction site April 2019





Back to School News      Print News Article
Contact Us
Lancaster City School District345 East Mulberry Street
Lancaster, OH 43130