At Thomas Ewing, permanent electrical power is being set and inside electrical wires are being installed.  In the cafeteria section of the building, water lines, sprinkler system rough ins, windows and external brick are being installed.  HVAC water lines and sprinkler system rough ins are being installed in the gymnasium section.  Water lines are also being installed in the classroom and main entrance sections while window installation is in progress in the main entrance section.  

At General Sherman, the weather conditions have impeded progress over the past week.  In the two story classroom section of the building, structural steel installation was finished and passed inspection.  The underground electric and plumbing lines have been completed in the single story classroom section and have passed inspection as well.