Junior High Construction Update 5/29/19

At Thomas Ewing, grading has begun for the football field while earthwork on the turn lane, walks, and curbs along with electrical rough ins for light poles continues.  The exterior brick cleaning is complete and light devices are being installed throughout the building.  Ceiling grid and casework are being installed on the second floor of the two story classroom section of the building.  Temperature controls are being installed in the media center, water lines are being insulated in the cafeteria section, and technology wires are being installed in the stage.  In the gymnasium section, technology, speaker, and electric lines are being installed while water lines are being insulated and sprinkler lines are being installed.

At General Sherman, the exterior concrete masonry block walls are complete in the cafeteria section of the building.  Concrete masonry block walls are being erected in the gymnasium section and domestic water lines are being installed in the two story classroom section.  In the main entrance section, stud walls, overhead electrical conduit, air ducts, and electric wall boxes are being installed. HVAC water pipes and roof curbs are being installed in the single story classroom section.

Steve Wigton
Superintendent

General Sherman Front Entrance Archway - May 2019

General Sherman Front Entrance Archway

 

Thomas Ewing - Bus Loop is being asphalted

Thomas Ewing - Bus loop is asphalted

 