General Sherman JH Construction Update 1/22/2020

General Sherman JH site plan

At General Sherman, lights are hooked up, HVAC pipes are insulated, and caulking/sealing is complete on the second floor of the two story classroom section of the building.  On the first floor, lights are being hooked up, HVAC control valves are being wired, sprinkler drops are being installed, and ceiling grid is being installed. Data wire has been pulled and ceiling grid installed in the single story classroom section while HVAC chilled beam units are being hung.  The stage area drywall is complete, the dining room ceiling painted, and the kitchen hood is insulated.  Throughout the building, the metal roof is now complete.  

Steve Wigton
Superintendent