General Sherman Construction Update 1/29/20

General Sherman progress 1.28.20

Cabinets are being installed on the second floor of the two story classroom section of the building, while lights and devices are being installed on the first floor.  In the single story classroom section, HVAC chilled beams are being connected, while sprinkler drops, ceiling grid, and electrical devices are being installed.  In the main entrance section, the art room floor is finished, while HVAC chilled beams and electric wires are being installed.  In the gymnasium section, the concrete locker bases have been poured, sprinkler drops are being installed and the first coat of paint has been applied.  In the cafeteria section, the stage drywall is being taped and the concrete block walls are being prepared for painting.

Steve Wigton
Superintendent

 