General Sherman JH Construction Update 2/19/2020

General Sherman Site Plan

Cabinetry has been installed and door frames are being painted on the second floor of the two story classroom section. In the single story classroom section, cabinets and ceiling grids are being installed, as well as sprinkler drops being tested and water pipes insulated.  Sprinkler drops are also being tested in the main entrance section and lights are being installed.  Gymnasium equipment is being installed along with caulking, sealing and data wiring in the gymnasium section.  In the cafeteria section, the first coat of paint has been applied.

Steve Wigton
Superintendent

 

 