General Sherman Construction Update 4/22/2020

GS.construction site April 2020

In the two story classroom section, the elevator is being installed, the flooring is complete (except stairwells), and student lockers have been installed on the second floor.  Student lockers are also installed in the single story classroom section, data wiring is complete, and hallway flooring is being installed. Ceiling clouds are installed in the media center and ceiling tile is being installed in the main entrance section. The gymnasium floor is being prepared while lights and lockers are being installed in the locker rooms. Throughout the building, plumbing fixture installation, glass caulking, and A/V wiring are underway.  Pipes and control wires are being installed in the mechanical rooms.