Junior High Construction Update 8/7/19

At Thomas Ewing, tile flooring is being installed in the single story classroom section of the building and work has begun to install the elevator in the two story classroom section.  In the cafeteria section, the cafeteria ceiling clouds are installed while first coat painting and music area casework installation are underway.  Throughout the building, HVAC chilled beam unit insulation, control wiring, and water pipe insulation continue.  On the site, rear parking lot sidewalk installation, and site work for road widening, sidewalks, drives and topsoil respreading continue.  The building is on schedule to be opened this coming January.

At General Sherman, brick installation is complete in the single story classroom section of the building and external spray foam insulation is being applied to the two story classroom section.  In the gymnasium section, internal concrete masonry block walls, overhead electrical conduit, and HVAC ductwork are being installed.  Internal concrete masonry walls and kitchen area roof installation are underway in the cafeteria section.  Roof drain testing, electric branch line installation and preparation for window installation are underway throughout the building.  The building is on schedule to be open for the 2020-2021 school year.

Steve Wigton
Superintendent





Back to School News      Print News Article
Contact Us
Lancaster City School District345 East Mulberry Street
Lancaster, OH 43130